Mud gun installation on the mud tank

The installation of the mud gun on the mud tank is purposely to keep the flow of the drilling mud from one tank space to another space.  The mud gun that manufactured by GN Solids America LLC offer both in fixed or rotated spray set up for drilling mud operators to maximum the function of the  mud gun.
The set up spray of the mud gun can be either high pressure or the low pressure spray action by corporation of the mud feeding pump.  The size of high pressure mud gun is smaller then compare with low pressure kind of mud gun.  Both kind of mud gun equips with nozzles that are movable and it mounts on the mud tank with joint and connected with the pump it separate the drilling mud in jet form and mixing the drilling fluid in the pool of mud to keep the drilling mud consist mixed.

The nozzle of the mud gun it comes with either fixed spray direction or changeable
 Way of direction.  The kind that is fixed direction got the mixing line of hydraulic function.  Its difference is the mud gun placed in the two diagonal, nozzle directions parallel to the vertical tank wall tank. It can have the set up of layer of rotation of the drilling fluid.  In the high direction set up, the jet spray can be sure of convention of the drilling fluid. 
The direction-changeable nozzle drilling mud gun is by the in pipe, tube, crosshead, paired turned pipe with threaded joints, can change the nozzle and two layer of composition, the gun body through the ball bearing and the in pipe is connected with. The fluid comes through the in pipe; the nozzle heads start in specific speed to the different direction concludes the function of the mud gun.  The speed of spray it determine on drilling fluid pressure, mud density and the mud flow.
GNNJQ Series manufacture by GN Solids America LLC provides supplemental or primary mixing in mud tanks depending on the number being used and the pit size.
GN solids control produced mud handling equipments and mud tanks are mainly used for cleaning and recycling the used driling fluids from the well bore. The mud handling equipments range including:
Shale shaker, mud cleaner, desander, desilter, vacuum degasser, Mud Gas Separator, jet shearing unit, mud agitator, decanter centrifuge, shear pump,vertical G cuttings dryer.
If you need mud handling equipments with mud tanks and solids control system, pls contact with GN solids control in Beijing, China

Tuesday, March 1, 2016

Mud Cleaning system for oil drilling progect

GN Solids Control produce all of the solids control products, eg. Shale shaker, desander, desilter, mud cleaner, decanter centrifuge, agitator, etc . GN several phase solids control mud system is working in more than 60 countries and locations with good working efficiency and reliable lifetime.

GN Solids Control four period mud recycling system which includes below parts.

Part one particular: shale shaker working on mud tanks, as the first cycle mud separation equipment. Looking for different type shale shaker intended for option. Including
a. 3 deck panel shaker that is certainly professional for diamond drilling, or other simple structure project.
b. 3 decks panel shaker which can be intended for workover rig and other task.
c. 4 deck panel shaker which is most popular intended for oil drilling circulation mud system and this can also intended for drilling waste management.

Aspect 2: Desander working following shale shaker to give additional treatment, as the second stage mud cleaning equipment. We also provide different type desanders for solution.
a. desander without terrace shaker, cheaper price.
udemærket. desander with deck shaker, reasonable price with higher efficiency



Part 3: desilter doing work after desander to give even more treatment, as the third level mud cleaning equipment. We in addition have different type desitler for alternative.
a. desilter without veranda shaker, cheaper price
c. desilter with deck shaker, reasonable price and higher efficiency.

Remark: we can also offer mud cleaner which is combination of desander & desilter. Smaller presence, but better performance.

Part several: Decanter centrifuge after desilter to give further treatment, since the fourth phase mud cleaning implement. We have different type centrifuge intended for options.
a. GNLW223 infant mini centrifuge for diamonds drilling
b. GNLW363 centrifuge which is most popular model intended for solids control / drilling waste management, GNLW363 will be replacement for Derrick DE1000 centrifuge, etc .
c. GNLW453 as well as GNLW553 is GN significant bowl big volume centrifuge for special requirements
g. GNLW452 centrifuge is central speed centrifuge which is specialist for barite recovery with regard to oil drilling.

Any needs, pls contact us freely.


Monday, February 22, 2016

Drilling fluid management during the winter cold weather

The installation of solids control drilling mud recycle system to meet the oil well drilling requirement in different stage of well drilling. The drilling fluid tanks mixer, butterfly valves need to be easy to use.
Base on the provisions of the garbage pit dug well, the size of garbage pit cannot be smaller than requirements of the design.

To make sure the safety of operators, it needs adjusting calibration of rotation direction of the motors that connected to the spindle flange ring. The start use of desander and desilter, and the drilling fluid decanter centrifuge before pre-heating of steam pumps and the pipelines.
The circulation of the drilling fluid, it reserves and distribution system work of insulation.
The ground measurement, maintenance and the handling to ensure the stability of performance of drilling fluid is base on strict implementation of the design of drilling fluid program that strengthen the daily management of the drilling fluid.  
The slurry and bentonite must be pre-hydration of 24 hours.
The filtrate loss reducer and plugging agent to add amount to be enough to maintain the stability of the borehole by increase the drilling fluid input. 

The personals that work on drilling mud system need to be increase compare with the drilling operation in the summer time by use mud scraper, blowout prevention box to reduce the waste.
Make sure strengthen the drilling fluid material reserves and management works, the reserves should be sufficient to prepare more than 50 cubic meters of drilling fluid.
The timely manner to remove the drilling cuttings in both desander and desilter cones to make sure that the conical tank liquid discharge port clearance.

To complete testing variety of drilling fluid equipments ensure ease of use for drilling mud recycling system operators.

Sunday, January 31, 2016

Welcome to meet with GN in CIPPE at booth E2200

With a nice begining of 2016, welcome to pay a visit to GN in CIPPE, snabel-a booth E2200. Details seeing that below:
Address: New The far east International Exhibition Center, Beijing; No . 88, Yuxiang Route, Tianzhu, Shunyi District, Beijing
Event Time: March 29-31, 2016
GN Booth Number: HALL E2 -E2200, presentation area area 272m2.
Booth Area: http://public.cippe.com.cn/static/hall/2016bj/hall_e2.jpg
Appointment Email: sales@gnsolidscontrol. com
GN Factory Place: 40KM to the Exhibition Centre (40 Minutes Drive)
Along with prediction on the market development, GN have made several big actions before other solids control suppliers. No matter GN is often a leader on this or not, GN have been the first, the leader for a lot of things. Been the initial API certified company, the 1st solids control supplier possess office & wearhouse with Houston, the first one have competent verticle cuttings dryer intended for waste mangament, the first one supply by china manufacturer who supplied waste management equipment to Baker Barnes. Also if only comparing the marketplace for oversea from China, GN must be the biggest one. Right after exported to over 60 nations, have been known by a lot more customers, engineers, and getting worldwide reputation.


Before men and women told us that we researched, and found you, then currently all new customers told us all, we are recommended by many reliable engineers, friends.
This is visit GN booth as well as check the products by yourself. Discovering is beliving, that is anything you always say, as easy to discover the production capacity, and if a number of manufacuturer is ready for your own order, for big orders not really. The facility is good or ready enough for production acturate equipment, suppliers great / qualified enough with regard to higher tech equipment.
In conclusion, Meet with GN people, and pay attention to the reason you can work with GN.

Monday, January 25, 2016

Cost-effective Shale Shaker Screen for Sale 20-30% Off

Shaker Screen is among the very often uses wear areas for drilling process. While starting the drilling method, the shaker screen will be installed on the shale shaker unit to separate the reliable particles in drilling water. The fine holes in screen panel could mass the solids larger than the opening size, while the liquid could possibly go through easily. On olive oil field, most of the shale shaker unit is using 3 or 4 panel screens. According to different condition of the actual drilling fluids and utilization, the driller need generate inventory of the spare shaker screen.
It will be good to obtain the shale shaker screen from the first shale shaker supplier once are willing to spend much cash on it. There is another way to find the replacement screen from the OEC screen manufacturer. This would spend less a lot on the cost of save screens, so that the drilling price would be greatly reduced.
GN Solids Control, definitely, is one of the companies of the shaker screens. Having nearly 10 years experience that manufactures the solids control gear and shaker screens, GN now could provide the substitution shaker screen for Derrick FLC 500 and 48-30 series, replacement screen intended for Swaco Mongoose and ALC series. No matter hook deprive or frame type, pre-tensioned or non-pretensioned. Many beneficial onsite level performance reactions proved the GN’s screen quality.


It is well known GN is a manufacturer who is maintaining improving the technology. Right after several years’ research in addition to kindly feedbacks from client, GN has improved typically the technology on shaker screen fabrication, which greatly enhances the shaker screen life time and minimize the processing cost. This kind of directly leads to the decrease of the screen price. GN is willing to share the power with all the clients by offered the full line screens using a 20-30% unit price lowering. That is really good news for your shaker screen requester.
GN is also able to provide the alternative shaker screen used on Cobra shaker, VSM300 shaker as well as FSI shakers. Besides, GN’s does have the screens with regard to own shale shaker product. If you have any request within the shaker screen, just contact us to get more information.

Sunday, January 17, 2016

Cycle of cleaning for the drilling fluid

Concept: The cleaning cycle of drilling fluid is to remove the harmful solid debris, reserve the clean drilling fluid to meet the demand of drilling fluid spec under the drilling process. Drilling fluid cleaning system is the term of all drilling fluid solids control equipments used in the oil drilling.

Function: To prevent the oil well from clogging, breaking, and decrease the drilling torque and friction resistance, reduce the pressure fluctuations of the empty suction, increase the drilling speed, extend the drilling bit life of use, and reduce wear and tear of the equipments.
Methods: The usual methods are mixture-thin methods, swap methods, machine methods and additive-chemical methods. Use different separation function machinery is  machine method is by using screening, centrifugal separation and gravity separation to separate the solid phase according to the different size and density, therefore, to control the solid phase in the drilling fluid.

1 The technical process of the drilling fluid cleaning system and the combination of the fluid cleaning equipment.
The technical process of complete group of drilling fluid cleaning system should meet the specification of five level solid phase control (screening, degassing, desanding, desilting, centrifuge) and the provoke the drilling fluid. The merger of each solids control equipment is very important, the through out of one to five level of mud cleaning equipment should each work with each other, and the spacing of the proper distance were is appropriate.  To have certain repeating cleaning during the cleaning process, make the smaller particles of the processing incomplete in the up one had been disposed in the next solids control equipment.


2 Drilling fluid cleaning cycles

The mud back from the opening of well through the pipeline and conveyed the drilling fluid to the shale shaker. The first phase of cleaning completed by shale shaker, then entered the mud tank, the drilling fluid flowed from the mud tank through the tank slot into the desander and desilter (if detect the present of gas, vacuum degasser will process to remove the gas) the fluid after processing of the centrifugal steps and through the tank slot enters the inhalation cabin.  The cleaned fluid then will reuse for lubricate and cooling the drill bit. 

Sunday, January 3, 2016

GN Closed Loop Zero Release System

As the restrictions with regard to dispose the drilling waste material from the oil and gas drilling is now more and more strict all over the world, particularly in developed countries and regions, the drilling companies as well as the oil related service businesses are more and more careful in disconnection with the drilling waste. It may be a trend that so-called zero discharged solutions is required for the oil and gas drilling market.
Among all the solids control and waste management producers in China, GN Solids Control is the first to create and develop the zero-discharged closed loop for treating the actual drilling cuttings. See specifics as below:
1 . GN complete solids control system including GN shale shaker, GN mud cleaner, GN middle speed decanter centrifuge and GN high speed decanter centrifuge. all drilling cuttings discharged from above mentioned products are collected by GNSC series screw conveyor for even more treatment instead of disposed.


installment payments on your GN drilling cuttings squander management system, it is useful for further treat the drilling cuttings. because the drilling cuttings from the solids control system are still wet. This system includes GNZS594HGE-LD drying shakers and GNLW363CG high speed decanter centrifuge for WBM solely. Or, GNCD930C vertical cuttings dryer and GNLW363CG Decanter centrifuge for both WBM and OBM.
The above mentioned two systems are enough for the majority of cases.
3. GN Dewatering unit and high speed dewatering centrifuge GNLW363CG-VFD. Dewatering product is a system for foloculating the extra fine particles in to larger ones in order to be connectors by the high speed decanter centrifuge. Like the item 2 is approximately the further treating with regard to drilling cuttings, the dewatering unit is for further healing the liquid.
4. GN Solidification unit and TDU Unit are respectively utilized for finally dispose the very well dried drilling cuttings in the drilling cuttings waste management system.